(Jan. 13, 2025) -- 111th Avenue Northeast is expected to be paved this Friday, Jan. 17. Asphalt was removed today in preparation, and residents have access to their driveways. Thank you for your patience, work is nearly complete on this project.
(Dec. 6, 2024) -- The infiltration well project is on schedule to complete work this winter. Final paving timeline is still to be determined.
(Oct 31, 2024) -- Drilling the infiltration wells is expected to begin Monday, Nov. 5. Drilling the wells is expected to take at least two weeks, and will be loud for nearby residents. Drilling is expected to begin at 8 a.m.
(Oct. 21, 2024) -- Construction is planned to begin on Monday, Oct. 28. 111th Avenue Northeast will be closed through the end of the year except for local access.
(April 19, 2024) -- The Kirkland City Council will consider on May 7 whether to award a construction contract to Northwest Cascade, Inc. If awarded, construction is expected to begin in June.