July 11-17
124th Avenue Northeast
Drivers traveling southbound on 124th Avenue Northeast are prohibited from turning left onto NE 120th Street. Kirkland’s contractor is widening 124th Avenue Northeast to five lanes and enhancing pedestrian and bicycle facilities.
Visit www.kirklandwa.gov/124avene
Northeast 116th Place (Goat Hill)
Goat Hill residents should expect road closures this week from 6 a.m. to 2:30 p.m. on Northeast 116th Place. PSE’s contractor is working on Northeast 117th Place from 3 p.m. to 12 a.m. and will have sections of the roadway closed during that work.
Visit www.kirklandwa.gov/goathill
Eighth Avenue West and Fifth Street West
Work is currently in two locations on 8th Avenue West: near the intersection with Market Street and between 3rd Street and 4th Street. Pedestrians on Market Street should use the east side to avoid pedestrian closures or follow detours. Flaggers are located at the intersections to allow for emergency vehicles.
Visit www.kirklandwa.gov/eighthavenuewestupgrade
Kirkland Avenue and Lake Street
Lake Street’s intersection with Kirkland Avenue is now open, and minor impacts to traffic flow are expected for delivery of materials throughout the remainder of construction.
Visit www.kirklandwa.gov/lakestreetpedscramble
Juanita Drive
Juanita Drive will be reduced to one lane periodically this week between 9 a.m. to 3 p.m. from Northeast 124th Street to Northeast 128th Street.
Visit www.kirklandwa.gov/juanitadrivecorridor
Fifth Avenue South and Eighth Street South
Kirkland's Fifth Avenue South and Eighth Street West water main contractor is alternating traffic until mid-July on Eighth Street South and a short section of Railroad Avenue.
Strickland and Sons crews are working from 7 a.m. to 5:30 p.m., Monday through Thursday.
Visit www.kirklandwa.gov/5aves-8sts
100th Avenue Northeast
OMA Construction, over the next two weeks, will have intermittent disruptions to access to Northeast 144th Lane as crews work to install soldier pilings for a new wall on the west side of 100th Avenue Northeast. The Kirkland contractor is alternating traffic at various locations between Northeast 137th and 145th streets. The legal speed limit through the construction zone is 25 miles per hour.
Visit www.kirklandwa.gov/100thavedesign